37 years of major-project engineering

Josten Magloire Wandji — Electromechanical engineer (ENSP Yaoundé), statutory manager of XP-NOVA SARL. National Order of Electrical Engineers (ONIGE) — registration A001703.

1989–1999

Project officer at the DGTC (Cameroon's Directorate-General of Major Works): technical and financial supervision of public facilities — including the Yaoundé city water supply (Nyong intake, network, water towers) and high-rise ministerial buildings.

1999–today

Project director at GEQUIPS: design supervision of the technology packages of major facilities — airports (Malabo, Ouagadougou-Donsin, Nsimalen, Douala, Bangui), stadiums, campuses, institutional headquarters, urban networks (Mongomeyen, Equatorial Guinea).

2008–today

Technical expert for APAVE: MEP expertise and technical inspection (buildings, industry, public facilities).

2010–2012

Technical expert to the National Public Procurement Commission (compliance of tender documents and bid evaluation reports).

2005 · 2010

Public programme audits in Gabon: Public Investment Budget (4 provinces) and support to the Treasury audit.

Countries of experience: Cameroon · Burkina Faso · Gabon · Equatorial Guinea · CAR · Congo.

GEQUIPS references

Nine assignments documented in donor format

Extracted from the official reference sheets of GEQUIPS SARL (a shareholder of XP-NOVA): verifiable periods, service values, staffing and clients.

New Ouagadougou-Donsin airport

Burkina Faso

Technical design supervision (technology packages)

Complete aerodrome: 80 buildings (120,000 m²), utilities, runways — 34 MW installed electrical capacity. Full design of power, low-current, HVAC and plumbing systems.

Period
2012–2013 (12 months)
Services
FCFA 99m excl. tax
Team
14 experts

Client: EGIS Cameroon

Rehabilitation of the Yaoundé Omnisport stadium

Cameroon

Technical design supervision and works control

30,000-seat stadium (CAF/FIFA compliance) and R+2 annex buildings. Full design of power, low-current, HVAC, plumbing, sound, lighting and safety systems.

Period
2015–2016 (15 months)
Services
FCFA 160m incl. tax
Team
22 experts

Client: EGIS Cameroon

Olembé Olympic sports complex (COSO)

Cameroon

Works control — drawings approval (power, low-current, plumbing, HVAC)

60,000-seat complex: main stadium, training pitches, gymnasium, Olympic pools, 5* hotel — turnkey construction (PICCINI).

Period
2017–…
Services
FCFA 8m incl. tax
Team
5 experts

Client: EGIS Cameroon (EGIS International, delivery supervision)

École Normale Supérieure, Maroua

Cameroon

Technical design supervision (buildings and utilities)

University campus of 25 buildings on 63 ha: full design of power, low-current, HVAC and plumbing systems for buildings and utilities.

Period
2008–2011 (12 months of services)
Services
FCFA 79m excl. tax
Team
8 experts

Client: EGIS Cameroon

CSPH headquarters building

Cameroon

Technical design supervision and works control

R+6 building: full design of the technical systems (power, low-current, HVAC, plumbing, sound, lighting, safety).

Period
2001–2007 (36 months)
Services
FCFA 72m incl. tax
Team
8 experts

Client: EGIS Cameroon

SNI high-rise rehabilitation (R+18)

Cameroon

Technical design supervision and works control

R+18 high-rise: complete technical systems, lifts, generator sets.

Period
2002–2003 (15 months)
Services
FCFA 75m incl. tax
Team
10 experts

Client: EGIS Cameroon

CAA headquarters — design

Cameroon

Technical design supervision

R+8 building with 3 basement levels: full design of the technology packages.

Period
2009–2010 (6 months)
Services
FCFA 35m incl. tax
Team
8 experts

Client: EGIS Cameroon

CAA headquarters — works control

Cameroon

Works control (power, low-current, plumbing, HVAC) — factory acceptance of equipment in Spain

R+8 building with 3 basement levels.

Period
2013–2016 (16 months of services)
Services
FCFA 32m incl. tax
Team
5 experts

Client: EGIS Cameroon

Total E&P headquarters — Brazzaville

Congo

Technical design supervision (detailed design phase)

R+7 building with 2 basements: full design of the technical systems.

Period
2017 (6 months)
Services
FCFA 34m incl. tax
Team
9 experts

Client: EGIS Cameroon

Engagement framework — applicable to all the sheets above

Assignment delivered by GEQUIPS SARL (shareholder of XP-NOVA SARL), Mr Wandji Josten Magloire as project manager. Capacity mobilisable by XP-NOVA through the statutory capacity-commitment mechanism and the technical support agreement.

Mobilisation mechanism

How these capacities serve your programmes

The articles of association of XP-NOVA SARL expressly provide for mobilising the technical, professional and human capacities of its shareholders — first among them GEQUIPS SARL — or of third parties, upon written commitment of availability, in accordance with procurement rules and the requirements of technical and financial partners. A technical support agreement binds the two structures.

In practice: when an ODT territorial programme requires airport, hydraulic or public-facility engineering, these references and the corresponding experts are mobilised in the forms expected by donors (CVs, reference sheets, written commitments).

Let's talk about your territory

Describe your territory and your ambition: a first response within 48 working hours.